Similar to manually completed discharge moves, you can enter move times for manually completed loads. However, unlike manually completed discharge moves, manually completed load moves are completed at the planned move time. If you have the XPS Equipment Control Module, XPS completes moves automatically when a hatch clerk performs the work using a radio data terminal (RDT).
For more information on completing moves, see the manual Navis N4: Vessel Administrator and User Guide.
To enter move times for manually completed loads:
Select the Magnifying tool .
In the Quay Commander window, click a work-queue block containing loads.
Alternatively, you can select load moves in a yard scan view.
In the Work Queue window that opens, select the load moves.
Select Planning Complete Move.
XPS completes the selected moves at the planned move time.